The Scoular Co.

Coolidge, KS

This project added 50,000 BPH shuttle train unloading and loadout capability, along with a 500,000 bushel capacity jump form concrete grain bin. On this project, HABCO, Inc. fabricated all spouting, platforms, diverters, stairs, etc. Features on the project include: 50,000 BPH gravity dump pit with 24′ long dump grate to receive product from rail cars and from trucks. 50,000 BPH leg discharges to the new jump form grain bin and to the existing slip form annex. 50,000 bph discharge on the new jump form bin to the new leg. 50,000 BPH belt conveyor below the existing slip form annex to the new leg. 50,000 BPH bulkweigher, sampler and hydraulic loadout spout.