• This facility upgrade added additional storage in the form of a new jump form concrete tank.

• A truck receiving pit and truck load out was also added at this time. A new receiving leg was installed to service the entire facility.

• The jump form concrete tank uses a Kanal bin unloading system that also serves as an aeration system.

• An upper fill conveyor was added to the tank and connected to existing equipment located on top of the existing bin.

• The truck load out system utilizes a Schuld/Bushnell 5,000 bushel overhead load out bin located above the new truck receiving pit.

• HABCO fabricated spouting connects the entire facility together.