• Project added over 450 thousand bushel of storage capacity with two (2) new jump form concrete tanks.

• This facility upgrade added two (2) new jump form concrete tanks to an existing facility. Over 450 thousand bushel of storage capacity was added in this upgrade.

• The new bins are tied into the existing facility through the use of drag conveyors.

• Three (3) new drag conveyors where added at bin top level for receiving. These drags are tied into the existing leg and provide receiving for existing bins at the facility.

• An additional two (2) drag conveyors where added at ground level for reclaim. These new drags tie back into the existing reclaim drag conveyor.

• Final bin cleanout is performed by a sweep auger located on the floor of both new bins. These augers discharge into the new reclaim conveyors. There are also truck load out spouts on both new bins.

Request a Quote