• This project encluded upgraded legs, distributor, spouting, and related structure.

• This project entailed replacing two receiving legs, support tower, manlift, and related equipment.

• The customer provided the new equipment for this upgrade.

•┬áThe customer at this location could not have the facility offline for any period of time, so a majority of this work was done around the current working equipment.

• With the new tower support system in place, the tower went up around the existing elevators and manlift. Once up, one of the current legs was removed, and a new leg installed in its place. Then the same was done for the remaining leg. This allowed the customer to keep operating on one leg.

• Remaining equipment such as distributors, diverters, and spouting was changed in the same fashion.

• The man lift that was once housed between the legs was replaced with a new unit installed inside the tower.

• Existing spouting was replaced with Habco spouting in both stainless and mild steel and was trussed where needed.

• All remaining structure or spouting not being removed was tied back into new structure and spouting as needed.